All in a Weekend’s Work
Our team had to replace the air handlers while the rehab hospital was operating, which meant we needed to replace them quickly. To streamline the installation process, the contractor installed the new equipment controls while the units were still on the ground, which reduced the time needed to actually install the units on the roof. The hospital was back up and running much sooner than if we had installed those components once the air handler was in place on the roof.
A Money-Saving Solution
Neither of the original air handlers were connected to the hospital’s emergency power supply, so we added one of the new units to the emergency generator. However, it looked like the hospital may need to purchase a new generator with more capacity to support the new system. We worked closely with ACHA to develop a long-term plan that satisfied the hospital’s future emergency power needs, as well as ACHA’s safety concerns, but didn’t bust Brooks’ budget.
Installation Certification
At the end of the project Gresham Smith’s commissioning team verified that the air handlers were installed correctly and that the new equipment operated efficiently and according to the owner’s project requirements. After preparing pre-functional checklists and performing functional performance tests, we confirmed that the system was good to go and ready to provide a breath of fresh air for rehab patients. It was so good to go, in fact, that Gresham Smith is currently working on replacing eight additional air handlers at the hospital.